Obstructions
The table below lists all the obstructions to navigation
on the Union and Forth and Clyde canals, from east to west. It also gives the
current projected dates of restoration, and thumb-nail images of some
obstructions.
The table is now colour coded. Red indicates an
obstruction on which restoration work has not yet begun, blue indicates
an obstruction which is currently under restoration, and green indicates a
former obstruction which has now been removed.
Some obstructions now have a page of their own,
with chronological pictures of the restoration work going on there. Click the
links to see pages about:
Union Canal
| Name of obstruction | Description |
Projected date of restoration | Picture |
| Leamington Bridge |
Derelict lifting bridge | ? |
 |
| Kingsknowe Road |
Culvert under road | Completed |
 |
| Wester Hailes |
Over 1 mile of canal infilled | Completed |
 |
| M8 |
Culvert under M8 Motorway | Completed |
 |
| Greendykes Road |
Culvert under road | Completed |
 |
| Vellore Road |
Culvert with 4'6" headroom | Completed |
 |
| A801 |
Culvert under road | Completed |
 |
| Falkirk Interchange |
Link between canals infilled | Early 2002 |
 |
Apart from the obstructions listed above, the Union Canal
has survived in remarkably good condition since its closure in 1965. The absence
of locks or opening bridges has obviously meant that there was less to go
wrong with it, and unlike the Forth and Clyde Canal, the water is still at its
original level along the whole length of the waterway. All this means that
apart from clearing the blockages, the only other major work to reopen the
canal will be dredging.
Forth and Clyde Canal
There are no longer any obstructions to navigation on the Forth and
Clyde Canal - it was reopened in May 2001. However, I have left the obstructions table here to
let people have a glimpse of what the canal was like before its restoration.
| Name of obstruction | Description |
Projected date of restoration | Picture |
| Grangemouth |
Over 1 mile of canal infilled | Completed |
 |
| Abbot's Road |
Culvert under road in lock 4 | Completed |
 |
| Bainsford Bridge |
Culvert under road | Completed |
 |
| Merer's Bridge |
Road built across lock 8 | Completed | N/A |
| Camelon Road |
Culvert under road | Completed |
 |
| Union Road |
Road built across lock 16 | Completed |
 |
| Bonnybridge |
Culvert with 4' headroom | Completed |
 |
| Castlecary Bridge |
Derelict swing bridge | Completed |
 |
| A80 |
Culvert under road | Completed |
 |
| Wyndford Bridge |
Fixed bridge over Lock 20 | Completed |
 |
| Auchinstarry Bridge |
Derelict swing bridge | Completed |
 |
| Twechar Bridge |
Derelict lifting bridge | Completed | N/A |
| Auchendavie Water Main |
Pipe crosses canal, only 4' headroom | Completed | N/A |
| Hillhead Bridge |
Derelict swing bridge | Completed | N/A |
| Townhead Bridge |
Culvert under road | Completed | N/A |
| Cadder |
Low bridge | Completed | N/A |
| Balmuildy Road |
Low bridge | Completed | N/A |
| Cleveden Road |
Culvert with 4' headroom | Completed |
 |
| Great Western Road |
600yd infill, including locks 31 and 32 | Completed |
 |
| Duntreath Avenue |
140yd infill, including lock 36 | Completed |
 |
| Argyll Road |
Low bridge | Completed |
 |
| Clydebank Footbridge |
Low bridge | Completed |
 |
| Kilbowie Road |
Culvert under road | Completed | N/A |
| Trafalgar Street Footbridge |
Low bridge | Completed | N/A |
| Dalmuir East Bridge |
Culvert under road | Completed |
 |
| Erskine Ferry Bridge |
Derelict swing bridge | Completed |
 |
Note: the dates given above are provisional only. I'll
try to keep them as up to date and accurate as possible, but they are by no
means a guarantee of when the blockages will be removed.